FAQs for Concrete and Asphalt EPDs
General Purpose of EPD Requirements
- Why is Caltrans requiring EPDs for hot mix asphalt and concrete?
- The California Department of Transportation (Caltrans) aims to
achieve carbon neutrality by 2045. Collecting EPD data helps quantify
the global warming potential (GWP) of materials, measured in carbon
dioxide equivalents. This information will assist in setting future GWP
benchmarks by material type and location and inform future contract
requirements.
Project Eligibility
- Which projects require EPD submittals for hot mix asphalt and
concrete?
-
EPD submission requirements apply to projects that meet all of the
following criteria:
- Bid opening date: After February 1, 2025
- Total bid amount: More than $1 million
- Original working days: 175 or more
- Material Quantity Thresholds
- At what material quantities must EPDs be submitted?
- EPDs are required when materials meet the following thresholds:
Hot mix asphalt: 2,250 tons from a plant per job mix formula
Concrete: 250 cubic yards from a plant per mix design
Submission Deadlines
- When must EPDs be submitted?
- EPDs must be submitted within 30 days of initial material placement on the
project.
- What happens if an EPD is not submitted on time?
-
If an EPD is not submitted within 30 days, a $6,000 performance failure withhold will be
assessed by the resident engineer for each missing EPD.
- If the missing EPD is submitted before contract acceptance, the withhold will be returned.
- If the missing EPD is not submitted by contract acceptance, the withhold becomes a permanent
deduction.
Submission Process
- How should contractors submit EPDs?
- Contractors must submit
EPDs through the EPD Data Collection System
Relation to Buy Clean California Act (BCCA)
- Are EPDs for hot mix asphalt and concrete part of the Buy Clean
California Act?
- No, the Buy Clean California Act (BCCA) applies to reinforcement and
structural steel to ensure that materials do not exceed the maximum
allowed GWP values set by the Department of General Services (DGS).
For hot mix asphalt and concrete, EPDs are only required for data collection purposes and are not
subject to GWP limits at this time.
Data/EPD Validity for Long Projects
- If a project spans three years and EPDs expire in year
two, can EPDs valid at the project start be submitted for job completion?
- EPDs must be valid at the time of project quantity
submission, whether it is at the start, middle, or end of the project.
- If EPDs are revalidated mid-project with higher GWP
numbers, how should this be handled?
- The latest GWP numbers must be used wherever applicable.
Responsibility for Uploading EPDs and Project Information
- Who is responsible for uploading EPDs and project
quantity information?
- Caltrans contracts with the prime contractor. The prime
contractor may elect to delegate EPD and quantity submission
responsibilities to the supplier. The EPD website allows either party to
create an account and submit information.
- Should only the concrete producer upload EPDs to
minimize errors?
- While the concrete producer can upload EPDs, the
contractor is ultimately responsible for ensuring that project information
is uploaded. Suppliers may not always have project details at the time of
EPD input, especially when submitting EPDs in bulk before project
identification.
Quantity Submissions
- How often should quantity information be submitted
(e.g., monthly, quarterly, or at the end of the project)?
-
A one-time submission, either based on the purchase
order or after delivering the final quantity, is an acceptable frequency
for Caltrans.
- How should discrepancies between ordered and delivered
quantities be handled in submissions? Should the "Quantity" field reflect
actual delivered amounts or estimated values?
- Submissions should reflect the actual delivered quantity. A
one-time submission after final delivery is the expected reporting method.
Clarifications can be provided in the comments to ensure clarity.